Analisis Produktivitas Dan Biaya Alat Berat Pada Penanganan Long Segment Jalan Sapta Marga Kampung Besar Kecamatan Banda Mulia
DOI:
https://doi.org/10.55616/prince.v5i1.1112Keywords:
Heavy Equipment, Productivity, Time Duration, Equipment Cost, Bina Marga Method 2023Abstract
Heavy equipment plays an important role in accelerating construction processes and reducing operational costs. Equipment such as dump trucks, motor graders, vibrator compactor rollers, and water tank trucks significantly influence project completion time. However, initial planning often does not match field conditions, resulting in increased costs and delays. Therefore, an analysis of heavy equipment productivity is necessary to ensure efficient utilization and cost optimization. This study aims to analyze the productivity, implementation time, and cost of heavy equipment in the Long Segment Handling Project for routine maintenance, periodic maintenance, and road reconstruction on Jalan Saptamarga – Kampung Besar, Banda Mulia District, specifically for subbase (LPB) and base (LPA) layers over a 1,000-meter section. The analysis of productivity and equipment costs was conducted using the Bina Marga 2023 method. The results show that the productivity of dump trucks is 30.42 m³/day, motor graders reach 975.20 m³/hour for LPB and 989.00 m³/hour for LPA, vibrator compactor rollers achieve 928.20 m³/day for LPB and 702.84 m³/day for LPA, while water tank trucks reach 450.00 m³/day. The LPB work requires 3 working days using 14 dump trucks and one unit each of motor grader, compactor roller, and water tank truck. Meanwhile, LPA work is completed in 2 days using 12 dump trucks and one unit of each supporting equipment. The rental costs per day are Rp 2,356,235.39 for dump trucks, Rp 3,467,735.73 for motor graders, Rp 2,846,290.20 for vibrator compactor rollers, and Rp 2,367,435.18 for water tank trucks. The total equipment rental cost is Rp 125,006,269.65 for LPB and Rp 73,912,571.55 for LPA, resulting in an overall cost of Rp 198,918,841.20.
References
[1] Abduh, M., Manajemen Proyek Konstruksi. Bandung: ITB Press, 2013.
[2] Callahan, M., Quirk, R., and Rowings, J., Construction Project Scheduling. New York: McGraw-Hill, 2000.
[3] Caterpillar Inc., Performance Handbook – Edition 49. Illinois: Caterpillar Tractor Co., 2020.
[4] Chandra, A., dkk., “Evaluasi Perhitungan Produktivitas Alat Berat pada Pekerjaan Jalan,” Jurnal Teknik Sipil, 2023.
[5] Direktorat Jenderal Bina Marga, Pedoman Perencanaan Tebal Perkerasan Lentur. Jakarta: Kementerian PUPR, 2022.
[6] Federal Highway Administration (FHWA), Construction Equipment and Methods Guide for Roadway Work. Washington, D.C.: FHWA, 2018.
[7] Hardiyatmo, H. C., Pemeliharaan Jalan Raya. Yogyakarta: Gadjah Mada University Press, 2011.
[8] Kassem, A., dkk., “Produktivitas Alat Berat dalam Proyek Konstruksi,” Jurnal Infrastruktur, 2021.
[9] Kementerian Pekerjaan Umum dan Perumahan Rakyat, Harga Satuan Dasar Peralatan (HSD) dan Pedoman Analisis Biaya Operasional Alat Berat. Jakarta: Kementerian PUPR, 2023.
[10] Peurifoy, R. L., and Schexnayder, C., Construction Planning, Equipment, and Methods. New York: McGraw-Hill, 2010.
[11] Peraturan Presiden Republik Indonesia Nomor 12 Tahun 2021 tentang Pengadaan Barang/Jasa Pemerintah.
[12] Putra, A. M., “Estimasi Penggunaan Alat Berat pada Pekerjaan Agregat Lapis Pondasi Kelas B Jalan Simpang Pertamina – Pulau Birandang,” Tugas Akhir, 2020.
[13] Razak, S., dkk., “Analisis Pengelolaan Alat Berat dalam Proyek Infrastruktur,” Jurnal Teknik Sipil, 2023.
[14] Rostiyanti, Manajemen Alat Berat. Jakarta: Penerbit Erlangga, 2008.
[15] Sadek, M., dkk., “Produktivitas Peralatan Konstruksi,” Jurnal Rekayasa Sipil, 2022.
[16] Setiawan, B., Soeparyanto, H., and Prasetia, R., “Analisis Biaya dan Produktivitas Alat Berat pada Pekerjaan Pengaspalan,” Jurnal Teknik Sipil, vol. XX, no. X, 2019.
[17] Sukirman, S., Perkerasan Jalan Raya. Bandung: Nova, 1999.
[18] Suparno and Widyanto, A., “Analisis Produktivitas Alat Berat untuk Pekerjaan Jalan,” Jurnal Transportasi, 2019.
[19] White, D. J., Heavy Construction Equipment Productivity and Methods. Iowa: Iowa State University Press, 2015.
[20] Yoder, E. J., and Witczak, M. W., Principles of Pavement Design. New York: John Wiley & Sons, 1975.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 PRINCE : Journal of Planning and Research in Civil Engineering

This work is licensed under a Creative Commons Attribution 4.0 International License.
Ciptaan disebarluaskan di bawah Lisensi Creative Commons Atribusi 4.0 Internasional.