Heavy Equipment Productivity, Equipment Quantity, Road Paving, Implementation Duration

Abstract

Road infrastructure plays a vital role in supporting economic growth and facilitating community mobility. Matang Seping Village in Aceh Tamiang Regency suffers from severely damaged roads, hindering the distribution of agricultural and fishery products. To address this issue, a road paving project on the Matang Seping–Pelita route was carried out, requiring careful planning and efficient use of heavy equipment. This study aims to analyze the utilization and productivity of heavy equipment used in the road paving project. The analysis focuses on identifying the types of heavy equipment employed, calculating productivity based on the 2023 guidelines from the Ministry of Public Works and Public Housing (PUPR), and determining the number and operational duration of each equipment unit. The equipment used for the prime coat work includes a compressor and asphalt sprayer, while the base course layer (Asphalt Concrete-Base Course) uses a dump truck, asphalt finisher, tandem roller, and pneumatic tire roller. The results show varied productivity levels, with the asphalt sprayer reaching 13,695 liters/hour and the asphalt finisher 134.46 tons/hour. All equipment was operated over two days, with quantities adjusted to project needs, including 12 dump trucks to ensure the smooth implementation of fieldwork.

References

Alat Marka Jalan, “Asphalt sprayer mini,” alatmarkajalan.com, Jan. 2022. [Online]. Available: https://www.alatmarkajalan.com/2022/01/asphalt-sprayer-mini.html

Badan Pusat Statistik, Dampak Infrastruktur Jalan terhadap Perekonomian Daerah. Jakarta: BPS, 2021.

Bank Dunia, The Economic Impact of Road Infrastructure Investment. Washington D.C.: World Bank, 2021.

Dikonindo, “Air Compressor Airman PDS 185 S,” [Online]. Available: https://www.dikonindo.co.id/alat-konstruksi/air-compressor-airman-pds-185-s/

Direktorat Jenderal Bina Marga, Pengelolaan Jalan Berkelanjutan di Indonesia. Jakarta: Kementerian PUPR, 2020.

P. A. Fransiskus, “Analisis produktivitas alat berat pekerjaan pengaspalan akses jalan masuk Bendungan Napun Gete,” Skripsi, Universitas Nusa Nipa, Maumere, 2021.

Global Berdikari Jaya, “Alat Berat Sakai TS200 Roller,” [Online]. Available: https://www.globalberdikarijaya.com/products/alat-berat-sakai-ts200-roller-j24109

Indoquip, “Asphalt Finisher Sumitomo,” [Online]. Available: https://www.indotrading.com/indoquip1/asphalt-finisher-sumitomo-p434030.aspx

Inti Karya Karisma, “Tandem Roller Bomag BW141AD,” [Online]. Available: https://www.intikaryakarisma.com/product/jual-tandem-roller-bomag-bw141ad2-kap-79t-6262194

M. S. Juwita, “Analisis produktivitas dan biaya penggunaan alat berat pada pelaksanaan pekerjaan lapisan perkerasan lentur (Studi kasus: Proyek peningkatan struktur jalan Sirombu-Afulu),” Skripsi, Universitas Medan Area, Medan, 2021.

Kementerian Pekerjaan Umum dan Perumahan Rakyat, Laporan Kondisi Jalan Nasional dan Strategi Pemeliharaan. Jakarta: PUPR, 2022.

Kementerian Pekerjaan Umum dan Perumahan Rakyat, Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum dan Perumahan Rakyat. Jakarta: PUPR, 2023.

S. F. Rostiyanti, Alat Berat untuk Proyek Konstruksi, 2nd ed. Jakarta: Rineka Cipta, 2008.

Srikandi Group, “Dump Truck FUSO FN 527 ML (6x4),” [Online]. Available: https://srikandi.com/assets/upload/FUSO%20FN%20527%20ML%20(6%20X%204)/5807d288830d9_5807d288831c4.pdf

Widiastuti, “Produktivitas waktu kerja alat berat pada pekerjaan peningkatan Jalan Kembang Tubanan Kabupaten Jepara,” Skripsi, Universitas Islam Nahdlatul Ulama Jepara, 2019.

S. F. Yayan, “Menghitung produktivitas pemakaian alat berat untuk pengaspalan (Studi kasus: Pekerjaan reservasi Jalan Bukit Tinggi – Batas Sumut Kab. Pasaman),” Skripsi, Universitas Ekasakti Padang, 2018.

Downloads

Published

07/31/2025

How to Cite

Agusti, E., Rajib Muammar, & Iqbal. (2025). Analisis Produktivitas Alat Berat Pada Pekerjaan Pengaspalan Jalan Matang Seping - Pelita Kabupaten Aceh Tamiang. Journal of Planning and Research in Civil Engineering, 4(2), 602–612. https://doi.org/10.55616/prince.v4i2.1008

Issue

Section

Articles