Comparative Study of the Fast Track Method with the Crash Program Method in Accelerating Time and Costs
DOI:
https://doi.org/10.55616/prince.v3i2.800Keywords:
acceleration, fast track, crash program, time, costAbstract
In many projects, delays are common, so it's important to make efforts to speed up the process and avoid them. This study investigates two methods of acceleration: the Fast Track method and the Crash Program method. The normal duration for this project is 180 days with a total cost of Rp. 14,666,588,288.29. The study uses MS Project to identify critical path activities that can be accelerated. The Fast Track method reduced the project time to 149 days at a cost of Rp. 14,287,701,424.18, while the Crash Program method reduced it to 144 days at a cost of Rp. 14,318,586,553.16. The study compares the time and cost outcomes of the two methods. The difference is due to the Fast Track method not incurring an increase in direct costs, only reducing indirect costs by changing predecessors. On the other hand, the Crash Program method resulted in additional direct costs but reduced indirect costs by adding 2 hours of overtime work.
References
Dwiretnani, Annisaa, Elvira Handayani, and Niko Saputra. 2023. “Evaluasi Penjadwalan Waktu Proyek Pembangunan Gedung Menggunakan Critical Path Method (CPM).” Jurnal Talenta Sipil 6(2): 391.
Ervianto, W. I. (2005). Manajemen Proyek Konstruksi (edisi revisi), Yogyakarta: CV. Andi offset
Fitrianto, Rahmat, and Dan Tuti Sumarningsih. 2016. “Penjadwalan Proyek Konstruksi Dengan Metode Penjadwalan Precedence Diagram Method (PDM) Dan Perhitungan Waktu Dengan Program Evaluation and Review Technique (PERT)(Studi Kasus?: Proyek Pembangunan Gedung TK Sultan Agung-UII Tahap II, Nglanjaran, Sleman).” Universitas Islam Indonesia.
Gede Wira Hadinata, Mayun NadiasaIda Ayu Rai Widhiawati. 2013. “View of Analisis Faktor-Faktor Penyebab Pembengkakan Realisasi Biaya Terhadap Rencana Anggaran Pelaksanaan Pada Proyek Konstruksi Gedung.” Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil, 2(2): 1–8. https://ojs.unud.ac.id/index.php/jieits/article/view/5620/4264.
Luthan, S., Putri, L., Sc, M., & Syafriandi, S. T. (2006). Aplikasi Microsoft Project untuk Penjadwalan Kerja Proyek Teknik Sipil. Yogyakarta: Andi.
Malifa, Yusuf, Ariesides K.T. Dundu, and Grace Y Malingkas. 2019. “Konstruksi Menggunakan Metode Crashing ( Studi Kasus?: Pembangunan Rusun IAIN Manado ).” Jurnal Sipil Statik 7(6): 681–88.
Mastura. 2011. “Manajemen Risiko Dalam Proyek Konstruksi.” Jurnal SMARTek 9(1): 39–46.
Munir, Mochamad Iqbal. 2012. “Evaluasi Kinerja Proyek Recondition Fire Water Pump P2226 JA Menggunakan Pendekatan Nilai Hasil Di PT Taka Turbomachinery Indonesia.” : 1–21.
Nur Rafi, Muhammad et al. 2022. “Project Planning Proyek Pembangunan Jalan Kawasan Industri Terpadu (KIT) Kabupaten Batang.” Jurnal Online Skripsi Manajemen Rekayasa Konstruksi (JOS-MRK) 3(4): 27–32. https://jurnal.polinema.ac.id/index.php/jos-mrk/article/view/1083.
Perdana, Surya, and Arif Rahman. 2019. “Penerapan Manajemen Proyek Dengan Metode CPM (Critical Path Method) Pada Proyek Pembangunan Spbe.” Amaliah: Jurnal Pengabdian Kepada Masyarakat 3(1): 242–50.
Priska Olivia. 2019. “Analisa Percepatan Waktu Proyek Menggunakan Metode Crash ing (Studi Kasus?: Peningkatan Jalan Pelantaran Parenggean - Tumbang Sangai).” Jurnal Teknika 1(1): 1–12.
Putra, Yan., and Sri. Hartati. 2017. “Optimalisasi Waktu Dan Biaya Menggunakan Metode Least Cost Analysis Pada Proyek Peningkatan Jalan Lingkar Kota Dumai.” Jurnal Saintis Vol. 17 No(April): 100–112.
Rahayu, Aryati Puji, Endang Mulyani, and Budiman Arpan. 2018. “Analisa Percepatan Waktu Dengan Metode Fast track Pada Proyek Konstruksi.” JeLAST?: Jurnal PWK, Laut, Sipil, Tambang 5(3): 1–10. https://jurnal.untan.ac.id/index.php/JMHMS/article/view/30478.
Siswanto. 2007. Pengantar Manajemen. Jakarta: Jakarta Bumi Aksara.
Sitanggang, Natahanel, Simarmata Janner, and Lynna A Luthan Putri. 2019. Pengantar Konsep Proyek Untuk Teknik. Jakarta:Yayasan Kita Menulis.
Zuhriyah, Aminatuz, and Wateno Oetomo. 2022. “Analisis Percepatan Waktu Dengan Metode Fast Track Dan Crashing Pada Proyek Pt Graynenda Putra Karya.” Jurnal Kacapuri?: Jurnal Keilmuan Teknik Sipil 5(1): 341.
Published
How to Cite
Issue
Section
Copyright (c) 2024 PRINCE : Journal of Planning and Research in Civil Engineering

This work is licensed under a Creative Commons Attribution 4.0 International License.
Ciptaan disebarluaskan di bawah Lisensi Creative Commons Atribusi 4.0 Internasional.